Task Order 06
Planning & Architecture
- Design & Construction of 7th Division, IA 3rd Brigade Al Qa’im Iraq that consisted of 32 buildings, 16,400 sm under roof, 60 acres land developed.One (1) Light Infantry Brigade Headquarters
- Three (3) Rifle Company Headquarters
- Connected to National Power Grid and install two (2) 1,600Kva Generators.
- Water connected to Phosphorus Plant Water with 420,000 liter storage tanks.
- Fuel Point with 40,000 liter Benzene Bulk Storage and 120,000 liters Diesel Bulk
Storage. - Brigade and Rifle Company Billeting Facilities for Enlisted/NCO/Senior NCO/Officer level.
DFAC
- Battalion Medical Building
- Two (2) Bay Maintenance Facility
- Gymnasium
- Training Center
- Sunshades
01 Jul 07
Start date
06 Jul 08
Date completed
$44MM
Cost